The capital projects programme outlined in the Long Term Plan 2018-28 (LTP) includes a substantial investment in a range of projects. For the Annual Plan 2020/21, some projects have been brought forward, some will be rescheduled to a later date, and some have been cancelled, as they are no longer required.

Changes to the capital works programme

Table one: Variation between LTP year 3 and Annual Plan 2020/21

Activity names as used in the LTP Annual Plan 2020/21 ($000) Long Term Plan 2020/21 ($000) Change between LTP Year 3 and Annual Plan 2020/21 ($000)
Community and Visitor Experiences 19,717 72,754 -53,037
Water Supply 14,604 4,955 9,649
Transportation 13,290 15,048 -1,758
Wastewater 8,036 3,795 4,241
Property Assets 7,533 3,889 3,644
Stormwater 3,361 6,675 -3,314
Support Units  2,538 2,493 45
Other Infrastructure 2,070 2,164 -94
City Strategy  1,067 592 475
Total ($000) 72,216 112,365 -40,149

Table two: Changes over $500,000 to a project between LTP year 3 and Annual Plan 2020/21

Activity Group Details of changes over $500,000 to 2020/21
Water Supply 
  • Borefield No.1 Rising Main New project, $5 million from loans for a new pipe to connect the new bore field to the supply network to access good quality drinking water.

  • New Water Treatment Plants $2 million has been moved from 2019/20 as there are two treatment plants to be built and the timing of the second plant will be outside of 2020/21 and identified in the LTP budgets.

  • Borefield No.2 Land purchase $1.5 million has been moved from new Taradale borefields to fund this project.

  • New Napier Hill reservoir $1.5 million has been moved from 2019/20. This funding will be used to start the design and land designation process once land is secured.

  • New Bores in Awatoto $1.5 million – additional funding requirement arisen out of Water Supply Model and Water Supply Masterplan.

  • Awatoto Industrial & Phillips Rd Supply $800,000 additional requirement due to growth.

  • District Monitoring Project $560,000 additional budget approved as part of the Annual Plan 2019/20.

  • New Reservoir Western Hills $500,000 has been deferred to 2021/22 as this funding is part of the Mission development and won’t be needed until the new subdivision is built.

Stormwater 

  • Ahuriri Masterplan Project 11 Pandora Catchment Improvements $800,000 moved to 2021/22 because stormwater modelling is still underway.
  • Ahuriri Masterplan project 3 Improve Direct Outfalls - $800,000 moved to 2021/22 because stormwater modelling is still underway.
  • New Pump Station in Bay View $2.6 million deferred to 2021/22 because stormwater modelling and master planning needs to occur first.
  • Te Awa Structure Plan New requirement - $1 million additional funding for infrastructure to enable development in Te Awa, funded by development contributions.
Wastewater
  • Wastewater Treatment Plant Upgrade New requirement - additional funding of $2 million for urgent repairs.
  • Wastewater Outfall replacement Additional $1.9 million is required for investigations and design to address the outfall leak issue.
  • Sewer pipe renewal budget Moved to Wastewater Outfall pipe repairs budget - $500,000.
  • Pandora Industrial Main $700,000 moved from 2019/20 because further investigation is required before work can be specified and programmed. 
  • Te Awa Structure Plan $500,000 new requirement to fund infrastructure to enable development in Te Awa, funded by development contributions. 
Transportation
  • Te Awa Structure Plan New requirement - $800,000 additional funding for infrastructure to enable development in Te Awa, funded by development contributions.
  • Te Awa Avenue $1.2 million has been moved from 2019/20, as the project was deferred.
  • Intersection safety improvement projects $820,000 moved from 2019/20 as the work on Kennedy Road/Marewa Shops upgrade was unable to be completed this year.
  • CBD Development $4 million deferred until 2021/22 and 2022/23 for the Marine Parade Piazza and Emerson Street Upgrade to give adequate time to develop a masterplan for the CBD and to develop detailed designs for the individual projects.
Property Assets 
  • Ahuriri Masterplan Iron Pot Public Access - $4 million has been moved to 2020/21. In 2019/20 designs were developed which will be shared with Council and the community before moving to the detailed design stage. Funding ($4 million) for the works won’t be needed until this is done.
  • Inner Harbour Facilities Renewal - $2 million moved to 2021/22 while Inner Harbour Masterplan is finalised. This will inform what works and funding is required. Some budget has been retained to replace the pontoons at the Nelson Quay ramp.
  • Property Holdings Property Purchase New requirement - $1.8 million for potential property purchases
Community and visitor experiences
  • Reserves – Whakarire Ave Revetment $1.7 million has been moved from 2019/20 as the project was delayed due to further consultation with residents. An additional $500,000 has been added to the budget due to increased cost estimates, so the allocation for the project is now $2.2 million.
  • Napier War Memorial build $1 million moved from 2019/20 to allow time for a new concept design.
  • Kennedy Park – Main Ablution Block$650,000 moved from 2019/20 as not all construction will be underway in 2019/20.
  • MTG – New Collection Shelving $500,000 deferred until 2021/22 as the collection shelving is only needed once there is new storage (under the collection storage facility project).
  • Napier Library Rebuild $3.8 million deferred to 2021/22 as investigations are still underway regarding the Library as part of a Civic Precinct.
  • Napier Aquatic Centre Development $19.3 million moved out of 2020/21 due to project delay.
  • National Aquarium of NZ – Expansion project $33 million (includes projected external funding) moved out of 2020/21 with the project being reviewed.

Do you want to hear from us more often and have your say on other Napier projects?

Join our People's Panel

Disclaimers and Copyright
While every endeavour has been taken by Napier City Council to ensure that the information on this website is accurate and up to date, shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith. Some of the information available in this site is from the New Zealand Public domain and supplied by relevant government agencies. cannot accept any liability for its accuracy or content. Portions of the information and material on this site, including data, pages, documents, online graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced information or material is copyright to the respective provider.

© Napier City Council